How Long Does a House Extension Take? A Realistic Timeline

"How long will it take" is really two separate questions: how long before building starts, and how long building itself takes. Both matter for planning your life around a project, and both are routinely underestimated by homeowners comparing quotes.

Client Reviews

What Our Clients Say

★★★★★

“Pindi is an excellent tradesman. His attention to detail is second to none and he's a really nice guy to work with. Highly recommend.”

James Graham

★★★★★

“Pindi did a fantastic job with my kitchen. He understood my requirements from the start and I was very happy with the finished result. His workmanship was exceptional.”

Lisa Creek

★★★★★

“I used Pindi Sahota for a house conversion, all works were carried out professionally.”

Aniket Patel

Before Building Starts: 6–10 Weeks

  • ✓Free site visit and initial discussion — same week you enquire
  • ✓Fixed-price written quote — typically within 10 working days
  • ✓Permitted development check or planning application — immediate confirmation, or 8+ weeks if full planning is needed
  • ✓Structural design and Building Regulations drawings — 2–3 weeks
  • ✓Building Regulations application submitted — processed alongside early build stages

On Site: 10–22 Weeks Depending on Scope

Project TypeTypical Time on Site
Single storey kitchen extension10–14 weeks
Double storey extension16–22 weeks
Loft conversion (dormer)8–12 weeks
Garage conversion4–6 weeks
Whole-house renovationvaries by scope — typically 12–30 weeks

What Actually Causes Delays

In our experience, the build programme itself rarely slips significantly once started — the real risk to timescales sits upstream, in planning delays (where full permission is needed), structural engineer turnaround time, and client decision-making on kitchen/bathroom specification once the shell is up. We agree a clear programme before work starts specifically so you know what to expect and when.

FAQ

Related Questions

Can I speed up the planning process?

Pre-application advice from the council can flag issues early, but formal determination timescales are set by the authority, not the builder — we manage the application but can't shorten the statutory period.

Will weather delay my build?

Groundworks and roofing stages are the most weather-sensitive. We build realistic contingency into the programme rather than quoting an optimistic best-case timeline.

Ready to Start Your Project?

Free written quote from your local Berkshire building contractor — usually within 10 working days, depending on the size of your project.

✓ Every project backed by a 2-year workmanship warranty, honoured personally by the owner on site.